We were able to get everything except the new fan/light installed by our self-imposed 7/15 deadline and we're on track for the 7/22 deadline.
I'm a little worried about the spackle/sanding and the tile- those will likely take us longer than expected... so I'll be happy if we can get a head start on them!
By July 15th:
Install new fan/light
By July 22nd:
This mirror is gone! New pictures soon! |
Install drywall to walls -Mike's working on today!
By August 5th:
Purchase tile, grout
Tape joints
Spackle & sand
By August 12th:
Purchase wood flooring
Install tile around shower/tub
Install shower/tub fixtures
By September 2nd:
Paint wainscoting pieces
Install wood floor
Install door & window molding
Install wainscoting
Install toe moldings
By September 9th:
Paint walls & moldings
Install shower curtain rod
By September 23rd:
Purchase Mirror
Install vanity
Install sink & tub fixtures
Install toilet
Install light fixtures
Install face plates
By October 1st:
Install drywall to foyer ceiling & walls
Finishing touches & decorating in bathroom