And the ending date is... October 1- Booo!!!!
And that's if everything goes smoothly (which it NEVER does!)
So with our expectations adjusted, here's the To Do List on a timeline, to keep us on track.
We gave a little bit of cushion- knowing that we have to figure some of this out by trial & error.
Hopefully there will be some overlap and we've allotted enough time!
We're doing pretty well so far (Knock on wood!)
By July 15th:
Connect electric to fan/light
Complete install of vent pipe in bathroom & attic
By July 22nd:
Waterproofing & wall board installed ahead of schedule! Will post details soon... |
Rip out old vinyl floor
Level joists
Install new sub-floor
Install drywall to walls
By August 5th:
Purchase tile
Purchase sink fixtures
Purchase molding pieces
Tape joints
Spackle & sand
By August 12th:
Purchase wood flooring
Install tile around shower/tub
Install shower/tub fixtures
By September 2nd:
Paint wainscoting pieces
Install wood floor
Install door & window molding
Install wainscoting
Install toe moldings
By September 9th:
Paint walls & moldings
Install shower curtain rod
By September 23rd:
Purchase Mirror
Install vanity
Install sink & tub fixtures
Install toilet
Install light fixtures
Install face plates
By October 1st:
Install drywall to foyer ceiling & walls
Finishing touches & decorating in bathroom