Showing posts with label Reveal. Show all posts
Showing posts with label Reveal. Show all posts

Monday, October 8, 2012

Bathroom Reveal

It's finally done!  It took us nearly 4 months, but it was total DIY and we're SOOOO happy with the results!



If you remember, here's where we started with this bathroom:










It feels so much bigger now!  I guess because the wallpaper vines are no longer creeping in on us!

Some more "After" shots...

The subway tile:


We picked up two iron hooks from this shop while we were on vacation in the Outer Banks this summer.
(In addition having cool antique-y & gift items, the owner of the shop wrote the "Captain Stumpy" children's books.  We stopped in to get the newest one, which he signed for the boys.)

The seahorse is for the kids to hang their robes while taking their baths.

The big hook is mounted on a wood plaque because the back of the iron hook wasn't perfectly flat.  It wouldn't sit flush to the wall & was really wobbly.
A minor setback that didn't deter us... Mike carve out some of the wood on the plaque so that the hook could nestle in there. Then he secured the plaque to the wall.  It's sturdy now!

 I was going to hang these baskets as shelves on the right side of the vanity, but they stuck out too far from the wall.
So, they've been relocated to under the vanity for keeping the extra towels & washcloths.







To complete the beach-y theme, we re-hung our black & white vacation photos.
Bonnie took new ones for us this summer, so I might be swapping some out once I order prints.





Of course, there are still a few little things that I want to tweak... like changing the door hardware, once I find the reproduction or replacement parts that we're missing.

But, we're ready to call it FINISHED!

Here's the final timeline/To Do list (All crossed out- yay!!!)

By July 15th:
Purchase wainscoting, drywall & wall board Complete!
Purchase sink/vanity & toilet Complete!
Purchase new light/fanwhite outlets & switches Complete!
Run electric from basement to attic (prep for finishing attic rooms) Complete!
Secure pex & wire to inside foyer wall (had run out of brackets) Complete!
Complete PVC caps on old pipes in basement Complete!
Finish stack in the foyer & insulate heating pipes
  Complete!
Complete install of vent pipe in bathroom & attic  Complete! 


By July 22nd:
Purchase shower/tub fixtures, shower curtain rod Complete!
Tar paper & waterproof shower/tub Complete!

Install wall board to shower/tub Complete!
Install new outlets & light switches Complete!
Rip out old vinyl floor   Complete! 
Level joists  Complete!  
Install new sub-floor  Not Needed!
Take down mirror  Complete! 
Install drywall to walls  Complete! 

By August 5th:
Purchase tile, grout & supplies
  Complete!   
Purchase sink fixtures Complete!
Purchase molding pieces  Complete!
Tape joints 
   Complete!  
Spackle & sand  Complete!   

By August 12th:
Purchase wood flooring-
  Complete!
Borrow tile cutter Complete!
Install tile around shower/tub Complete!   
Purchase paint/supplies  Complete!   
Install shower/tub fixtures Complete!  

By September 2nd:
Paint wainscoting pieces Complete!  
Install wood floor- 
Complete! 
Install door & window molding  Complete!   
Install w
ainscoting -  Complete!   
Install toe moldings-
 Complete!  
Install crown molding- decided against, seemed like too many moldings


By September 16th:
Paint walls & moldings
Complete!   
Install shower curtain rod
- Complete!
Install new fan/light Complete! 

By September 29:
Purchase Mirror
- Complete!    
Install vanity- Started!
Install sink
 fixtures- Complete!
Install toilet- Complete!
Install vanity light fixtures
Complete!   
Purchase & Install face plates
- Complete!

Purchase & Install plantation shutters- Complete! 
Make & Install door saddle- Complete!    

By October 8th:
Finishing touches & decorating in bathroom
- Complete!







Related posts:










Featured on:
The Dedicated House