We made lots of progress this past weekend:

  • installed the shower curtain rod 
  • installed both sets of lights, including the fan (with the help of our very kind neighbor!)
I love that you can't really tell the fixture is a fan!
These used to point down,
but I wanted more room for the mirror.
It should look more balanced this way!













  • painted the door

  • fixed the window sill (a chunk of wood was missing from where the old vanity cut in front of it)



  • purchased & installed plantation shutters to the window- thrilled that these were on clearance for $17!







  • purchased the mirror & brought the vanity into the room.  



The vanity is going to be the tricky party- new holes needed to be drilled in the floor & in the vanity base to run the pipes.  
We're working on that this week...  



Here's the updated To Do list:

By July 15th:
Purchase wainscoting, drywall & wall board Complete!
Purchase sink/vanity & toilet Complete!
Purchase new light/fanwhite outlets & switches Complete!
Run electric from basement to attic (prep for finishing attic rooms) Complete!
Secure pex & wire to inside foyer wall (had run out of brackets) Complete!
Complete PVC caps on old pipes in basement Complete!
Finish stack in the foyer & insulate heating pipes
  Complete!
Complete install of vent pipe in bathroom & attic  Complete! 


By July 22nd:
Purchase shower/tub fixtures, shower curtain rod Complete!
Tar paper & waterproof shower/tub Complete!

Install wall board to shower/tub Complete!
Install new outlets & light switches Complete!
Rip out old vinyl floor   Complete! 
Level joists  Complete!  
Install new sub-floor  Not Needed!
Take down mirror  Complete! 
Install drywall to walls  Complete! 

By August 5th:
Purchase tile, grout & supplies
  Complete!   
Purchase sink fixtures Complete!  
Purchase molding pieces  Complete!  
Tape joints 
   Complete!  
Spackle & sand  Complete!   

By August 12th:
Purchase wood flooring-
  Complete!
Borrow tile cutter Complete!
Install tile around shower/tub Complete!  
Purchase paint/supplies  Complete!   
Install shower/tub fixtures Complete! 

By September 2nd:
Paint wainscoting pieces Complete!  
Install wood floor- 
Complete! 
Install door & window molding  Complete!   
Install w
ainscoting -  Complete!   
Install toe moldings-
Complete!  
Install crown molding- decided against, seemed like too many moldings


By September 16th:
Paint walls & moldings
Complete!   
Install shower curtain rod
- Complete!
Install new fan/light Complete! 

By September 23rd: (let's make it 9/29!)
Purchase Mirror
- Complete!  
Install vanity- Started!
Install sink
 fixtures
Install toilet
Install light fixtures
- Complete!   
Purchase & Install face plates (Lowe's didn't have the ones we wanted in stock- BOO!)

By October 1st:
Finishing touches & decorating in bathroom


By October 8th: 
(giving ourselves an extra week on this part!  Too much other stuff going on during the next few weekends!)
Install drywall to foyer ceiling & walls


Related posts:
Before pics
Project Timeline
Bathroom Demo
Bathroom Shopping

Tar paper & Wallboard installation
Photos of progress- 7/23
Picking the flooring
Bathroom tile
8/7 Update 
8/15 Update
 
Flooring installed
 
Wainscoting installed

Primed
Painted

No comments:

Post a Comment